Redevelopment of the passenger building and adaptation of the accessibility of the Roma Tuscolana station
Implementing party
Project description
In the context of the 2025 Jubilee, a series of interventions on the Tuscolana station system were carried out, mainly focusing on specific upgrades and maintenance works. The planned activities were:
- Refunctionalisation of the internal spaces of the Traveller Building: the internal spaces of the Traveller Building were upgraded to improve their functionality.
- Cleaning of internal and external surfaces: cleaning operations were carried out on the internal and external surfaces of the Via Adria Building, the underpasses and the Accessory Building, in order to guarantee a more welcoming and cared-for environment for travellers.
- Restoration of sidewalk shelters 2-3-4: The shelters on sidewalk 2-3-4 were restored in order to improve protection from atmospheric agents and ensure greater comfort for passengers while waiting.
The main objective of these interventions was to preserve and improve the conditions of the Tuscolana station system, ensuring a clean, functional and welcoming environment for passengers and visitors.
Status
Planning
Tender stage
Site
End of Work
Funding source
Rete Ferroviaria Italiana
Jubilee
Amount allocated
3.500.000,00 €
Details of financing
€ 0 Jubilee, € 3.500.000 RFI-MIT Program Contract Investment Part