Caput Mundi: Aurelian Walls tract Via Campania/Corso d'Italia
Implementing party
Project description
The section needs conservative restoration work to stop the mortar flaking off, the detachment of the face, the disintegration of the wall ridges and the presence of cracks/lesions due to infesting vegetation and deep root systems. Structural work will be carried out to restore the stability of several wall structures and the artistic and functional lighting system.
Specifically, the project includes the following works:
- preliminary cleaning operations;
- elimination of infesting vegetation and biological attacks;
- conservation works;
- constitutive reinforcement works;
- structural reinforcement;
- construction of an electrical and lighting system;
adaptation to legislation on architectural barriers, safety and fire prevention.

Status
Planning
Tender stage
Site
End of Work
Estimated completion date
Second Quarter 2026
Funding source
NRRP
Amount allocated
2.340.000,00 €